Sugar House Construction Projects

Sugar House Construction Projects

Sugar House Construction Projects

Updated report

August 25, 2025  

      Montaire (Formerly Alta Terra) (Formerly 24 Hour Fitness)

  • Location: Ashton Ave./1100 E.
  • Start Date: June 2022.
  • Est. Completion: Early Spring 2026.
  • Project description: Residential (Approx. 340 units)
  • Update: The south building is completed and now available for occupancy.  The full height has now been reached and framing is progressing inside the north building. Through traffic between Ashton Ave. & 1100 East is now open in both directions.  Expected project completion is early spring 2026. Parking will remain available along the park frontage on 1100 East. 2 Hour Parking signs have been installed at the east end of Fairmont Park as well as “No Construction Parking” signs to discourage all-day parking by construction workers and are now placed on the east end of Ashton Ave.
  • Inquiries into availability and rental information can be directed to: montaireliving.com.

      

2100 South Road Re-construction Project

  • Location: 2100 South, 700 East-1300 East. 
  • Start Date: Early March. 2024 
  • Est. Completion: Fall 2025.
  • Project Description: Installing updated water and sewer lines and re-building long worn-out roadway, improving pedestriancrossing, and traffic calming.  
  • Update: Replacement of the roadway is now completed on both sides of the road between Lincoln St. and 700 East. Two-way traffic is now open on both east and west bound lanes between 700-900 E. Some work continues on landscape improvements and intersection crosswalks and is expected to be completed by mid-to-late August. Paving is completed and two way traffic between 900-1100 E. is expected to be restored by 8/29. The project is now targeted to be be substantially complete by end of September, six weeks ahead of schedule.

1300 East Roadway Repair Project

  • Location: 1300 East from 2100 S.-3000 S.
  • Start Date: April 21, 2025.
  • Est. Completion: Fall 2025.
  • Project Description: Roadway repair and re-paving, crosswalk improvements.
  • Update:  Work is now occurring between 2100 S. and the freeway exits/entrances and is being restricted to night time only, 8:00 p.m. – 6:00 a.m., to better accommodate the heavy volumes of traffic in those areas. The intersection at 2100 S./1300 E. will be closed during overnight hours Sunday – Friday, as well as either north or south bound traffic on 1300 East, depending on which half crews are working on. This section of work is expected to last 3-4 weeks.  Work was completed at the intersection of 1300 E./Highland Drive, a week ahead of schedule, and the intersection is now fully re-opened to traffic.             
  • Coming Attractions
  • The former Deseret Industries at Highland Drive/Sugarmont,  demolition occurring late fall ‘25.
  • The York Building, Simpson Ave./1100 E., demolition occurring late ‘25, new apartment construction early ‘26.
  • S Line extension project beginning early ‘26.

      For questions or reporting issues or concerns contact: Bill Knowles, SLC Community Ombudsman: 801-580-2626; [email protected]

Landon Clark
[email protected]