29 Nov Sugar House Construction Projects
Sugar House Construction Projects
Updated report
May 27, 2025
(Formerly) Alta Terra (Formerly 24 Hour Fitness)
Location: Ashton Ave./1100 E.
Start Date: June 2022.
Est. Completion: Spring 2026.
Project description: Residential (Approx. 340 units)
Update: The exterior work on the south portion of the project is completed and
interiors are currently being finished. This section of the project is expected to be ready
for occupancy by mid-to-late June of ’25. Inquiries into availability and rental
information can be directed to: montaireliving.com. Framing is progressing upward on
the north building. Through traffic on Ashton Ave. to NB 1100 East remains closed for
another one-two weeks while crews finish road and sidewalk improvements prior to
opening the south building for occupancy. Parking will remain available along the park
frontage on 1100 East . 2 Hour Parking signs have been installed at the east end of
Fairmont Park as well as “No Construction Parking” signs to discourage all-day parking
by construction workers and are now placed on the east end of Ashton Ave.
2100 South Road Re-construction Project
Location: 2100 South, 700 East-1300 East.mid-June
Start Date: Early March. 2024
Est. Completion: Fall 2025.
Project Description: Installing updated water and sewer lines and re-building long
worn-out roadway, improving pedestrian crossing, and traffic calming.
Update: Replacement of the roadway is now completed on the south side of the road
between Lincoln St. and 700 East. Two-way traffic is now shifted t the south side of
the street while crews demo and replace the asphalt on the north side. Completion of
this section is estimated by mid-June. Concrete work is now underway between
Lincoln and 1100 E. and will continue into mid-June, followed by the new roadway
placement. Beginning mid-June, traffic between 900-1100 E. will be reduced to one
way only, weatbound, for a period of six-eight weeks, with detours required for
eastbound traffic at 900 E. as the old road is taken up and replaced with new
pavement. The project remains on target to be completed by late August/mid-
September.
1300 East Roadway Repair Project
Location: 1300 East from 2100 S.-3000 S.
Start Date: April 21, 2025.
Est. Completion: Fall 2025.
Project Description: Roadway repair and re-paving, crosswalk improvements.
Update: Work is now underway and will be occurring in various locations along
the corridor. Work occurring between 2100 S. and the freeway exits/entrances
will be restricted to night time only, 8:00 p.m. – 6:00 a.m., to better
accommodate the heavy volumes of traffic in those areas.
Beginning approximately the first week of June the intersection at 1300
E./Highland Drive will be closed for up to six weeks while the multiple crossings
are repaired and re-paved. SB traffic will detoured at 2700 S.; NB traffic will be
directed to 1300 E.
Clean-up work:
Crews are finishing up assorted landscape and pavement striping projects as part of
the final touch-ups for the last two years’ extensive Highland Drive/1100 East
project. The last pieces are expected to be completed by the end of May
Disruptions should be minimal and infrequent.
For questions or reporting issues or concerns contact: Bill Knowles, SLC Community
Ombudsman: 801-580-2626; [email protected]