Sugar House Construction Projects

Sugar House Construction Projects

Sugar House Construction Projects

Updated report

June 26, 2025  

      Montaire (Formerly Alta Terra) (Formerly 24 Hour Fitness)

  • Location: Ashton Ave./1100 E.
  • Start Date: June 2022.
  • Est. Completion: Early Spring 2026.
  • Project description: Residential (Approx. 340 units)
  • Update: The exterior and interior work on the south portion of the project is completed and the unit is awaiting final inspections before opening in early July.  Inquiries into availability and rental information can be directed to: montaireliving.com. Framing is progressing upward and near topping off on the north building.            Through traffic on Ashton Ave. to 1100 East is now open in both directions. Parking will remain available along the park frontage on 1100 East. 2 Hour Parking signs have been installed at the east end of Fairmont Park as well as “No Construction Parking” signs to discourage all-day parking by construction workers and are now placed on the east end of Ashton Ave.

       2100 South Road Re-construction Project

  • Location: 2100 South, 700 East-1300 East. 
  • Start Date: Early March. 2024 
  • Est. Completion: Fall 2025.
  • Project Description: Installing updated water and sewer lines and re-building long worn-out roadway, improving pedestriancrossing, and traffic calming.  
  • Update: Replacement of the roadway is now completed on both sides of the road between Lincoln St. and 700 East. Two-way traffic is now open on both east and west bound lanes. Some work continues on landscape improvements and is expected to be completed by first week of July.  Traffic between 900-1100 E. will be reduced to one way only, westbound, for a period of six-eight weeks, with detours required for eastbound traffic at 900 E. as the old road is taken up and replaced with new pavement. The project remains on target to be completed by late August/mid-September.

1300 East Roadway Repair Project

  • Location: 1300 East from 2100 S.-3000 S.
  • Start Date: April 21, 2025.
  • Est. Completion: Fall 2025.
  • Project Description: Roadway repair and re-paving, crosswalk improvements.
  • Update:  Work is now underway and will be occurring in various locations along the corridor. Work occurring between 2100 S. and the freeway exits/entrances will be restricted to night time only, 8:00 p.m. – 6:00 a.m., to better accommodate the heavy volumes of traffic in those areas. 
  • The intersection at 1300 E./Highland Drive will remain closed for up to three more weeks while the multiple crossings are repaired and re-paved. SB traffic will detoured at 2700 S.; NB traffic will be directed to 1300 E.   

       Clean-up work:

  • Crews have completed assorted landscape and pavement striping projects as part of the final touch-ups for the last two years’ extensive Highland Drive/1100 East project. 

For questions or reporting issues or concerns contact: Bill Knowles, SLC Community Ombudsman: 801-580-2626; [email protected]

Landon Clark
[email protected]