Construction Projects

Construction Projects

Sugar House Construction Projects

Updated report

April 23, 2024

Sugar Alley – Lowe Development

  • Location: 2200 S. Highland Drive.
  • Start date: Fall 2020.
  •  Est. completion: Early 2025.
  • Project description: Mixed use residential.
  • Update: Re-construction continues on site with five floors are in place on the building and framing complete. Work is now focusing on the interior of the building. The re-build is expected to be completed by late 2024/early 2025. This will be a five-story building containing 200 luxury apartments with the ground floor dedicated to retail, including restaurants and a bike shop.  

Izzy South & North

  • Project Location: Approx. 550 E./2100 S.
  • Start Date: Late January ’22.
  • Est. Completion: Completed.
  • Project description: 2-70+ unit residential, townhomes and single floor, with small commercial component on west end, ground floor.
  • Update: The north side of the project is being occupied. The south side is also now complete with the outside, EB, lane open and the building ready for occupancy.

All travel lanes on 2100 South are now open to 700 East.

  The 21s

  • Project Location: 2000 E./2100 S.
  • Start Date: Mid-June2021.
  • Est. Completion: Maybe mid-June.
  • Project Description: Multi-unit residential.
  •  Update: The pedestrian walkway remains in place, now using the parking lane. Both WB lanes of 2100 South are open. The contractor continues work on finishing the south side of the project area. A new sidewalk is now in place along the 2100 East side and the 2100 South side of the project allowing full pedestrian access.

The north building is now expected to be completed and available for occupancy by mid-May. Two businesses will begin occupying the retail space, facing 2100 South, in mid-May, reportedly a gym and a candle making shop, with more retail shops to follow soon.

Work was completed over the spring break timeframe, as planned, replacing the ADA ramp at the corner of the intersection of 21st & 21st.

Alta Terra (Former 24 Hour Fitness)

  • Location: Ashton Ave./1100 E.
  • Start Date: June, 2022.
  • Est. Completion: Spring 2025.
  • Project description: Residential (Approx. 340 units)
  •  Update: One-way traffic (WB) continues on Ashton Ave. and the pedestrian walkway along the frontage of the south side property has been repaired and allowing for safe access, including ADA accessible, through the project site and adjacent staging area. Framing on the south portion of the project has begun and moving steadily forward across the top of the structure. Utility installations have progressed to the third phase, after completing the work on Ashton and Simpson, with work now focused on 1100 East, fronting Fairmont Park. Some temporary traffic obstructions will occur, however the current one-way traffic will continue to be in place. WB traffic has been fully restored to Simpson and Sugarmont ahead of schedule.

2 Hour Parking signs have been installed at the east end of Fairmont Park to discourage all-day parking by construction workers. Discussions are currently being held between the contractor and a nearby private property owner to arrange parking for construction workers.   

900 E./Sugarmont Project

  • Location: Approx. 2200 S./900 E.
  • Start Date: 9/23/22.
  • Est. Completion: Early Summer ’24.
  • Project Description: 4-Story, 45-unit apartment building.
  •  Update: The project work is now primarily on the interior of the building.

The Gallacher (former Art Studio Building)

  • Location: 700 East/Simpson Ave.
  • Start Date: 8/22/22.
  • Est. Completion: May 2024.
  • Project Description: Multi-unit (60+ units) residential.
  •  Update: This project is in the final stages and nearing completion. Final touches to the exterior finish are being made and the building near ready for occupancy.

Highland Drive/1100 E. Re-Construction Project (Phase II)

  • Location: 1100 East from 2100 South to Ramona Ave.
  • Start Date: January 2, 2024.
  • Est. Completion: May 2024.
  • Project Description: Reconstruction of the roadway and storm drains, with added bike lane infrastructure and improved crosswalks and ADA access.
  • Update: One-way traffic (NB) between 2100 South and Ramona Ave. is currently in place and will last through May, 2024. Storm drains on the west side are complete and   NB traffic is now shifted back to the west side of the street, over temporary asphalt while finishing flatwork is now being worked on the east side. The project remains on target to be completed by late May/early June.

2100 South Sewer Expansion (Phase I)

  • Location: 2100 South/1100 East- 2100 South/1200 East.
  • Start Date: Early September 2023.
  • Est. Completion: Mid-February 2024.
  • Project Description: Replacing the nearly 100-year-old main sewer line that runs in the middle of 2100 South.
  • Update: The first segment, between 1100 and 1200 East on 2100 South has been completed. Work has now been completed at the Douglas Street/2100 South intersection. Sewer lining work continues between 1700 -1900 East.      

1100 East Improvement Project

  • Location: 1700 South-900 South/100 East.
  • Start Date: May ’23.
  • Est. Completion: May ’24.
  • Project Description: Improving curb & gutter, storm drainage, crosswalks, and road re-paving.
  • Update:  Work has now begun on the northern portion, focused on the east side of the road, between 1300 and 900 South, and is expected to last into October of this year.   

Former Pizza Hut property(Formerly Dee’s Drive-In).

  • Location: 735 E. 2100 South.
  • Start date: May 2023.
  • Est. Completion: Spring 2024.
  • Project Description: Two restaurant spaces, one a drive through(pre-existing).
  • Update:  Cubby’s is now open for business on the west side of the property. The second building, on the east side of the property, is nearly complete and ready for occupancy as well.

2100 South Road Re-construction Project

  • Location: 2100 South, 700 East-1300 East.
  • Start Date: Early March. 2024
  • Est. Completion: Mid-to late 2025.
  • Project Description: Installing updated sewer lines and re-building long worn-out roadway, improving pedestriancrossing, and traffic calming + continuing replacement of old sewer lines . 
  • Update: Work is in full swing on the sewer pipe-lining segment moving from 800 to 1100 East. Roadway construction activity is also underway between 900 East and McClellan and, on another segment between 1100-1200 East.

One lane of traffic in each direction will generally be allowed on 2100 South throughout this project. However, there could be occasions of brief closures/detours in one direction, as made necessary by a particular construction activity occurring on that side of the road. Traffic on McClelland, NB from 2100 South, will remained closed until approximately May 3rd.       

Keep An Eye Out for Information On:

Former Snelgrove Ice Cream property

  • Location: 2100 S./800-900 E.
  • Project Description: Mixed use residential
  • Start Date: TBD
  • Est. Completion: Summer 2026.
  • Update: Demolition of the old structures on site is completed

Proposed project on 10th & Elm

Proposed project at the old Midas Muffler site.

Proposed project at the Wells Fargo Bank site.

For questions or reporting issues or concerns contact: Bill Knowles, SLC Community Ombudsman: 801-580-2626; bill.knowles@slcgov.com.

April 2024

Landon Clark
minnesotaute76@gmail.com