29 Nov Sugar House Construction Projects
Sugar House Construction Projects
Updated report
March 25, 2025
Sugar Alley – Lowe Development
- Location: 2200 S. Highland Drive.
- Start date: Fall 2020.
- Est. completion: Spring 2025.
- Project description: Mixed use residential.
- Update: Finishing work continues on the five-story building containing 200 luxury
apartments, with the ground floor dedicated to retail, including restaurants and a public
work out center. The re-build is expected to be completed and available for occupancy on
April 1. As of March 21, Hearth & Hill & Hill’s Kitchen restaurant spaces on the northeast
side of the building are now open for business!
(Formerly) Alta Terra (Formerly 24 Hour Fitness) - Location: Ashton Ave./1100 E.
- Start Date: June 2022.
- Est. Completion: Spring 2026.
- Project description: Residential (Approx. 340 units)
- Update: The exterior work on the south portion of the project is nearly completed.
This section of the project is expected to be ready for occupancy by mid-to-late May of
’25. Framing has now begun on the north building. As of Wednesday, March 26,
through traffic on Ashton Ave. to NB 1100 East will be closed for up to three weeks
while crews finish utility installations prior to opening the south building in mid-May.
Parking will remain available along the park frontage on 1100 East. 2 Hour Parking
signs have been installed at the east end of Fairmont Park as well as “No Construction
Parking” signs to discourage all-day parking by construction workers and are now
placed on the east end of Ashton Ave.
2100 South Road Re-construction Project - Location: 2100 South, 700 East-1300 East.
- Start Date: Early March. 2024
- Est. Completion: Fall 2025.
- Project Description: Installing updated water and sewer lines and re-building long
worn-out roadway, improving pedestrian crossing, and traffic calming. - Update: Roadway and waterline construction activity between 900 East and 700 East
is now completed. Curb, gutter, and sidewalk are currently being installed on the
north side of the street. The sewer line replacement is now complete and remaining
water line work from 900-1100 East will be completed shortly after the end of March.
Concrete work is slated to begin shortly after, followed by the new roadway
placement. Traffic will be reduced to one lane, each direction, with occasional
detours required as the old road is taken up and replaced with new pavement. The
project remains on target to be completed by late August/mid-September.
Clean-up work: - Crews will be seen in the first weeks of March on 1100 East and Highland Drive
finishing up assorted landscape and pavement striping projects as part of the final
touch-ups for the last two years’ extensive Highland Drive/1100 East project. The
last pieces are expected to be completed by the end of April - Disruptions should be minimal and infrequent.
For questions or reporting issues or concerns contact: Bill Knowles, SLC Community
Ombudsman: 801-580-2626; [email protected]