29 Nov Sugar House Construction Projects
Sugar House Construction Projects
Updated report
August 25, 2025
Montaire (Formerly Alta Terra) (Formerly 24 Hour Fitness)
- Location: Ashton Ave./1100 E.
- Start Date: June 2022.
- Est. Completion: Early Spring 2026.
- Project description: Residential (Approx. 340 units)
- Update: The south building is completed and now available for occupancy. The full height has now been reached and framing is progressing inside the north building. Through traffic between Ashton Ave. & 1100 East is now open in both directions. Expected project completion is early spring 2026. Parking will remain available along the park frontage on 1100 East. 2 Hour Parking signs have been installed at the east end of Fairmont Park as well as “No Construction Parking” signs to discourage all-day parking by construction workers and are now placed on the east end of Ashton Ave.
- Inquiries into availability and rental information can be directed to: montaireliving.com.
2100 South Road Re-construction Project
- Location: 2100 South, 700 East-1300 East.
- Start Date: Early March. 2024
- Est. Completion: Fall 2025.
- Project Description: Installing updated water and sewer lines and re-building long worn-out roadway, improving pedestriancrossing, and traffic calming.
- Update: Replacement of the roadway is now completed on both sides of the road between Lincoln St. and 700 East. Two-way traffic is now open on both east and west bound lanes between 700-900 E. Some work continues on landscape improvements and intersection crosswalks and is expected to be completed by mid-to-late August. Paving is completed and two way traffic between 900-1100 E. is expected to be restored by 8/29. The project is now targeted to be be substantially complete by end of September, six weeks ahead of schedule.
1300 East Roadway Repair Project
- Location: 1300 East from 2100 S.-3000 S.
- Start Date: April 21, 2025.
- Est. Completion: Fall 2025.
- Project Description: Roadway repair and re-paving, crosswalk improvements.
- Update: Work is now occurring between 2100 S. and the freeway exits/entrances and is being restricted to night time only, 8:00 p.m. – 6:00 a.m., to better accommodate the heavy volumes of traffic in those areas. The intersection at 2100 S./1300 E. will be closed during overnight hours Sunday – Friday, as well as either north or south bound traffic on 1300 East, depending on which half crews are working on. This section of work is expected to last 3-4 weeks. Work was completed at the intersection of 1300 E./Highland Drive, a week ahead of schedule, and the intersection is now fully re-opened to traffic.
- Coming Attractions
- The former Deseret Industries at Highland Drive/Sugarmont, demolition occurring late fall ‘25.
- The York Building, Simpson Ave./1100 E., demolition occurring late ‘25, new apartment construction early ‘26.
- S Line extension project beginning early ‘26.
For questions or reporting issues or concerns contact: Bill Knowles, SLC Community Ombudsman: 801-580-2626; [email protected]