29 Nov Sugar House Construction Projects
Sugar House Construction Projects
Updated report
November 25, 2024
Sugar Alley – Lowe Development
- Location: 2200 S. Highland Drive.
- Start date: Fall 2020.
- Est. completion: Spring 2025.
- Project description: Mixed use residential.
- Update: Finishing work continues on the interior of the building. The re-build is expected to be completed by early spring 2025. This will be a five-story building containing 200 luxury apartments with the ground floor dedicated to retail, including restaurants and possibly a bike shop. Urban Hill & Hill’s Kitchen restaurant spaces on the northeast side of the building is also moving along with their tenant buildout. Curb and gutter and cut-back parking has been restored across the front of the property.
Alta Terra (Former 24 Hour Fitness)
- Location: Ashton Ave./1100 E.
- Start Date: June 2022.
- Est. Completion: Spring 2026.
- Project description: Residential (Approx. 340 units)
- Update: Framing on the south portion of the project is completed and brick has been put in place on the lower half. . Work is now finishing up on the installation of a large water distillation tank to be installed at the entry to the Fairmont Dog Park parking lot and will allow the entry to that parking lot reinstated before Thanksgiving. Parking will remain available along the park frontage on 1100 East. 2 Hour Parking signs have been installed at the east end of Fairmont Park as well as “No Construction Parking” signs to discourage all-day parking by construction workers and are now placed on the east end of Ashton Ave.
Highland Drive/1100 E. Re-Construction Project (Phase II)
- Location: 1100 East from 2100 South to 1700 South.
- Start Date: January 2, 2024.
- Est. Completion: November 15, 2024.
- Project Description: Reconstruction of the roadway and storm drains, with added bike lane infrastructure and improved crosswalks and ADA access.
- Update: Completed!
2100 South Storm Drain Clean Out
- Location: 2100 South/1700 East- 2100 South/2200 East.
- Start Date: Early October 2024.
- Est. Completion: November 15, 2024.
- Project Description: Clean out debris accumulated in storm drains from sewer project
- Update: Completed!
1100 East Improvement Project
- Location: 1300 South-900 South/1100 East.
- Start Date: March ’24.
- Est. Completion: October ’24.
- Project Description: Improving curb & gutter, storm drainage, crosswalks, and road re-paving.
- Update: Completed!
2100 South Road Re-construction Project
- Location: 2100 South, 700 East-1300 East.
- Start Date: Early March. 2024
- Est. Completion: Mid-to late 2025.
- Project Description: Installing updated water and sewer lines and re-building long worn-out roadway, improving pedestriancrossing, and traffic calming.
- Update: Roadway and waterline construction activity remains active between 900 East and 700 East, center of the road and will continue throughout the winter months. The final phase of work on the segment between 1100-1300 East is now completed. Four lanes of traffic are fully open now between 900 and 1300 East.
For questions or reporting issues or concerns contact: Bill Knowles, SLC Community Ombudsman: 801-580-2626; [email protected]