Sugar House Construction Projects

Sugar House Construction Projects

Sugar House Construction Projects

Updated report

February 27, 2025  

Sugar Alley – Lowe Development

  • Location: 2200 S. Highland Drive.
  • Start date: Fall 2020.
  • Est. completion: Spring 2025.
  • Project description: Mixed use residential.
  • Update: Finishing work continues on the five-story building containing 200 luxury apartments, with the ground floor dedicated to retail, including restaurants and a public work out center.  The re-build is expected to be completed by late March/early April.  Urban Hill & Hill’s Kitchen restaurant spaces on the northeast side of the building are also moving along with their tenant buildout and expect to open their doors on March 17 for a “soft opening” followed by a grand opening planned for the next weekend.  

      Alta Terra (Former 24 Hour Fitness)

  • Location: Ashton Ave./1100 E.
  • Start Date: June 2022.
  • Est. Completion: Spring 2026.
  • Project description: Residential (Approx. 340 units)
  • Update: The exterior work on the south portion of the project is nearly completed and brick has been put in place on most of the building. This section of the project is expected to be ready for occupancy by mid-to-late May of ’25.  Framing has now begun on the north building. One way, west bound, traffic remains available on Ashton Ave. to NB 1100 East. Parking will remain available along the park frontage on 1100 East. 2 Hour Parking signs have been installed at the east end of Fairmont Park as well as “No Construction Parking” signs to discourage all-day parking by construction workers and are now placed on the east end of Ashton Ave.

       2100 South Road Re-construction Project

  • Location: 2100 South, 700 East-1300 East.
  • Start Date: Early March. 2024 
  • Est. Completion: Mid-to late 2025.
  • Project Description: Installing updated water and sewer lines and re-building long worn-out roadway, improving pedestriancrossing, and traffic calming.  
  • Update: Roadway and waterline construction activity between 900 East and 700 East is currently on holiday hiatus but will resume shortly after the beginning of the New Year.  The final phase of 2100 South road work, on the segment between 700-1100 East, is in full swing since the first of the year. Final work on the installation of the expanded sewer line is currently occurring and will immediately be followed by the new roadway placement. Traffic will be reduced to one lane, each direction, with occasional detours required as the old road is taken up and replaced with new pavement. The project remains on target to be completed by late August/mid-September.

       Clean-up work:

  • Crews will be seen in the first week of March on 1100 East and Highland Drive finishing up assorted landscape and pavement striping projects as part of the final touch-ups for the last two years’ extensive Highland Drive/1100 East project. The last pieces are expected to be completed by the end of April 
  • Disruptions should be minimal and infrequent.  

For questions or reporting issues or concerns contact: Bill Knowles, SLC Community Ombudsman: 801-580-2626; [email protected]

Landon Clark
[email protected]