29 Nov Sugar House Construction Projects
Sugar House Construction Projects
Updated report
April 29, 2025
Sugar Alley – Lowe Development
Location: 2200 S. Highland Drive.
Start date: Fall 2020.
Est. completion: Complete!
Project description: Mixed use residential.
Update: The re-build is completed and available for occupancy! Hearth & Hill & Hill and
Hill’s Kitchen restaurant spaces on the northeast side of the building are now open for
business!
(Formerly) Alta Terra (Formerly 24 Hour Fitness)
Location: Ashton Ave./1100 E.
Start Date: June 2022.
Est. Completion: Spring 2026.
Project description: Residential (Approx. 340 units)
Update: The exterior work on the south portion of the project is nearly completed.
This section of the project is expected to be ready for occupancy by mid-to-late May of
’25. Framing is progressing upward the north building. Through traffic on Ashton Ave.
to NB 1100 East remains closed for another one-two weeks while crews finish utility
installations prior to opening the south building in mid-May. Parking will remain
available along the park frontage on 1100 East . 2 Hour Parking signs have been
installed at the east end of Fairmont Park as well as “No Construction Parking” signs to
discourage all-day parking by construction workers and are now placed on the east end
of Ashton Ave.
2100 South Road Re-construction Project
Location: 2100 South, 700 East-1300 East.
Start Date: Early March. 2024
Est. Completion: Fall 2025.
Project Description: Installing updated water and sewer lines and re-building long
worn-out roadway, improving pedestrian crossing, and traffic calming.
Update: Replacement of the roadway is now occurring on the south side of the road
between Lincoln St. and 700 East with two-way traffic shifted t the north side of the
street. Completion of this section is estimated by first week in May. Work will then
move to the north side, shifting traffic lanes to the south. Concrete work is now
underway between Lincoln and 1100 E. and will continue into late May, followed by
the new roadway placement. Beginning mid-late May, traffic between 900-1100 E.
will be reduced to one way only, eastbound, for a period of six-eight weeks, with
detours required for westbound traffic as the old road is taken up and replaced with
new pavement. The project remains on target to be completed by late August/mid-
September.
1300 East Roadway Repair Project
Location: 1300 East from 2100 S.-3000 S.
Start Date: April 21, 2025.
Est. Completion: Fall 2025.
Project Description: Roadway repair and re-paving, crosswalk improvements.
Update: Work is now underway and will be occurring in various locations along
the corridor. Work occurring between 2100 S. and the freeway exits/entrances
will be restricted to night time only, 8:00 p.m. – 6:00 a.m., to better
accommodate the heavy volumes of traffic in those areas.
Clean-up work:
Crews will be seen in the first weeks of March on 1100 East and Highland Drive
finishing up assorted landscape and pavement striping projects as part of the final
touch-ups for the last two years’ extensive Highland Drive/1100 East project. The
last pieces are expected to be completed by the end of April
Disruptions should be minimal and infrequent.
For questions or reporting issues or concerns contact: Bill Knowles, SLC Community
Ombudsman: 801-580-2626; [email protected]