Road Construction Update

Road Construction Update



October 25, 2023
Upcoming Construction Activities
Highland Drive looking south near Simpson AvenueHighland Drive/1100 East Update:Highland Drive Phase 1, from I-80 to 2100 South, is on schedule to complete in November. Crews continue work in the 2100 South/Highland Drive intersection until then. Dominion Energy is relocating some conflicting lines in the northwest corner of the 2100 South/Highland Drive intersection and water and storm drain installation will follow. Two-way traffic will be restored to Highland Drive in November until Phase 2, from 2100 South to Ramona Street, begins in early 2024.
2100 South/1100 East IntersectionCrews are continuing work on the northwest corner of the intersection through this week. Underground utility work including storm drain, water line and gas line replacement or relocation is ongoing.
Traffic on 2100 South is currently using the south side of the roadway. Area drivers should be prepared for changes in traffic configuration.
Highland Drive 2100 South intersection traffic control map
Myriad of underground utilities in the 2100 South Highland Drive intersection.Myriad of underground utilities in the 2100 South Highland Drive intersection.
Underground utilities in the 2100 South Highland Drive intersection.
The Vue Parking Garage AccessThe Highland Drive access to The Vue parking garage has been reopened. We appreciate your patience while the crews poured the concrete curb and placed the final asphalt.
Safety ReminderTo assist with pedestrian accessibility near 2100 South and Highland Drive, crews have installed a temporary crosswalk at the intersection of 2100 South and Elizabeth Street (1155 East). Pedestrians should use extra caution while crossing at this new location. For safety, pedestrians should follow any posted detour sign.
Nearby Construction Activities
2100 South Traffic Restrictions; 1000 East to 1400 East
Crews will complete work between 1300 East and 1200 East by early November. Ground conditions west of 1300 East have slowed the work and we do not want to have traffic control impacting the business district during the busy holiday season. Work will resume between 1200 East and 1100 East in spring 2024. In late November or early December, crews will move to the east end of Phase 2 at Yuma Street. 2100 South will be reduced to one lane in each direction on the south side of the road while crews replace the pipe on the north side. Residents on the north side of 2100 South can expect some access interruptions while crews pass through the area.
To learn more, visit the project website or call the project hotline at 888-556-0232.Sugar House Traffic Calming Project
Beginning November, Salt Lake City Transportation will start a traffic calming project on various streets in Sugar House. This project will install speed humps, traffic islands, and other calming measures in the area. To learn more, visit the website.
Business Resources
The Construction Mitigation Grants program is available to businesses on or within one block of the Highland Drive project area. More information and applications are available at https://www.slc.gov/ed/constructiongrant/.
Contact the project team if you would like a poster, flier or map to assist your customers in navigating the construction.
The project team is coordinating closely with the Sugar House Chamber of Commerce to help businesses connect to available resources.
Check out Salt Lake City’s Successfully Navigating Road and Utilities Construction guide or reach out to us directly to share your questions or concerns.
Stay Informed
This project has a dedicated public involvement team to work with the public from the concept design through construction. Subscribe via email.Phone: 888.556.0232Email: [email protected]Website: www.HighlandSLC.org
Landon Clark
[email protected]