2700 South Reconstruction Update
These are the activities our construction crews will be working on over the next few weeks: Crews are currently lowering the utilities along 2700 South from 1700 East to Dearborne Avenue. Expect minor traffic delays through this area while crews are working. The sewer work...
21 July, 2019